Q. At a work site, statistical quality control of concretemeans

a. Measurement of risks to eliminate failures

b. Applying the theory' of probability to sample testing or inspection

c. Reduction in wastage of inspection costs

d. Reduction in costs for the removal of defects

  • b. Applying the theory' of probability to sample testing or inspection

Q. For the network shown in the given figure, the expected time for the activity

a. 1-2 is 4

b. 2-3 is 7

c. 3-4 is 8

d. All the above

  • d. All the above

Q. A critical ratio scheduling

a. Determines the status of each activity

b. Adjusts automatically changes in activity progress

c. Is a dynamic system

d. None of these

  • d. None of these

Q. Pick up the correct statement from the following:

a. Optimistic time estimate refers to activities

b. Pessimistic time estimate refers toactivities

c. Most likely time estimate refers to activities

d. All the above

  • d. All the above

Q. A golden rule for the procurement of construction stones, suggests

a. 100% at the site

b. 67% at the site and 33% under procurement

c. 50% at the site and 50% under procurement

d. 33% at the site and 67% under procurement

  • b. 67% at the site and 33% under procurement

Q. The time with which direct cost does not reduce with the increase in time is known as

a. Crash time

b. Normal time

c. Optimistic time

d. Standard time

  • b. Normal time

Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

a. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest starttime

b. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

c. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

d. All the above

  • d. All the above

Q. Interfering float is the difference between

a. Total float and free float

b. Total float and independentfloat

c. Free float and independentfloat

d. None of the above

  • a. Total float and free float

Q. While filling the tender for any work, the contractor considers

a. Site survey

b. Availability of construction materials

c. Availability of labour

d. All the above

  • d. All the above

Q. Pick up the incorrect statement from the following:

a. The various functions under each activity, are shown by one bar on Bar Charts

b. Bar chart establishes the interdependency of one event on another

c. Only approximate percentage of the completed work isreported

d. None of these

  • b. Bar chart establishes the interdependency of one event on another