Top 150+ Solved Construction Management MCQ Questions Answer

From 1 to 15 of 163

Q. In time-cost optimization of a project, crashing is done.

a. On all the activities

b. On all the activities lying on the critical path

c. Only on activities lying on the original critical path and having flatter costslopes

d. On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope

  • d. On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope

Q. Which of the following does not represent an activity?

a. Site located

b. Foundation is being dug

c. The office area is being cleaned

d. The invitations are being sent

  • a. Site located

Q. In resources levelling

a. Total duration of project isreduced

b. Total duration of project isincreased

c. Uniform demand of resources is achieved

d. Cost of project is controlled

  • c. Uniform demand of resources is achieved

Q. Sensitivity analysis is a study of

a. Comparison of profit and loss

b. Comparison of assets and liabilities

c. Change in output due to change in input

d. Economics of cost and benefits of the project

  • c. Change in output due to change in input

Q. Preliminary project report for a road project must contain

a. The detailed estimated cost based on detailed design

b. The several alternatives of the project that have been considered

c. The soil survey, traffic survey, concept design and approximate cost

d. The contract documents for inviting tenders

  • c. The soil survey, traffic survey, concept design and approximate cost

Q. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

a. Moist loam

b. Good common earth

c. Well blasted rock

d. Wet sticky clay

  • a. Moist loam

Q. In PERT analysis, the time estimates of activities and probability of their occurrence follow

a. Normal distribution curve

b. Poisson's distribution curve

c. Beta distribution curve

d. None of the above

  • c. Beta distribution curve

Q. Free float is mainly used to

a. Identify the activities which can be delayed without affecting the total float of preceding activity

b. Identify the activities, which can be delayed without affecting the total float of succeeding activity

c. Establish priorities

d. Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

  • b. Identify the activities, which can be delayed without affecting the total float of succeeding activity

Q. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

a. Concrete

b. Loose sand

c. Asphalt

d. Firm earth

  • b. Loose sand

Q. Which of the following earth moving machines has the shortest cycle time?

a. Drag line

b. Hoe

c. Clam shell

d. Dipper shovel

  • d. Dipper shovel

Q. Updating may result in

a. Change of critical path

b. Decrease of project completion time

c. Increase of project completion time

d. All of the above

  • d. All of the above

Q. The time by which a particular activity can be delayed without affecting the preceding andsucceeding activities is known as

a. Total float

b. Free float

c. Interfering float

d. Independent float

  • d. Independent float

Q. During the construction period, price variation clause in contracts caters to

a. Increase in rates of only importantmaterials

b. Variation in cost in materials element, labour element and petrol-oil-lubricantelement

c. Variation in total cost of the project on an ad hocbasis

d. Rate of inflation

  • b. Variation in cost in materials element, labour element and petrol-oil-lubricantelement

Q. Critical path method

a. Is an improvement upon bar chart method

b. Provides a realistic approach to daily problems

c. Avoids delays which are very common in bar charts

d. All the above

  • d. All the above