Top 150+ Solved Construction Management MCQ Questions Answer

From 46 to 60 of 163

Q. Railway projects are treated as

a. Light construction

b. Heavy construction

c. Industrial construction

d. None of these

  • b. Heavy construction

Q. Pick up the correct statement from the following:

a. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

b. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

c. The difference between total float and free float, is called interfering float

d. All the above

  • d. All the above

Q. For completion of a project, the critical path of the network represents

a. Minimum time

b. Maximum time

c. Maximum cost

d. Minimum cost

  • a. Minimum time

Q. Which one of the following represents an event?

a. Concrete cured

b. Fixing of door

c. Plastering of walls

d. Selecting sites

  • a. Concrete cured

Q. PERT is

a. An analytic in concept

b. Limited of event oriented diagrams

c. Used for research and development projects

d. All the above

  • d. All the above

Q. For the execution of a project, a contractor is

a. A person

b. A firm

c. An agency

d. All the above

  • d. All the above

Q. The constraints in case of resource smoothening operation would be

a. Resources

b. Project duration time

c. Both resources and project duration time

d. None of the above

  • b. Project duration time

Q. The time which results in the leasi, possible construction cost of an activity, is known as

a. Normal time

b. Slow time

c. Crash time

d. Standard time

  • b. Slow time