Top 150+ Solved Construction Management MCQ Questions Answer
Q. Power stations are generally treated as
a. Light construction
b. Heavy construction
c. Industrial construction
d. Electrical construction
Q. For a given size of bucket, the ideal output of a dragline will be least in
a. Moist loam
b. Sand and gravel
c. Good common earth
d. Wet sticky clay
Q. The time corresponding to minimum total project cost is
a. Crash time
b. Normal time
c. Optimistic time
d. Between normal time and crash time
Q. Select the incorrect statement.
a. Start float and finish float are always equal.
b. Total float can be either start float or finish float.
c. Start float and finish float need not be equal.
d. Start float and finish float are the differences between activity times and notevent times.
Q. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
a. Event
b. Free float
c. Dummy
d. Constraint
Q. PERT technique of network analysis is mainly useful for
a. Small projects
b. Large and complex projects
c. Research and development projects
d. Deterministic activities
Q. The independent float affects only
a. Preceding activities
b. Succeeding activities
c. The particular activity involved
d. None of the above
Q. Site order book is used for recording
a. Instructions by the executive engineers
b. Construction measurements
c. Issue of store equipments
d. Names of the casual labour
Q. The time by which activity completion time can be delayed without affecting the start ofsucceeding activities, is known as
a. Duration
b. Total float
c. Free float
d. Interfering float
Q. The part of a derrick crane include(i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
a. (i), (ii) and (iv) are correct
b. (ii), (iii) and (iv) are correct
c. (i), (iii) and (iv) are correct
d. (i), (ii) and (iii) are correct
Q. Works costing less than Rs. 20,000 are treated as
a. Any project
b. Major projects
c. Minor projects
d. All the above