Q. The time by which activity completion time can be delayed without affecting the start ofsucceeding activities, is known as (Solved)
1. Duration
2. Total float
3. Free float
4. Interfering float
- c. Free float
1. Duration
2. Total float
3. Free float
4. Interfering float