Q. The most suitable type of equipment for compaction of cohesive soils is

a. Smooth-wheeled rollers

b. Vibratory rollers

c. Sheep foot rollers

d. Tampers

  • c. Sheep foot rollers

Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

a. Started 5 days later

b. Completed 5 dayslater

c. Performed at slower rate in 15days

d. All the above

  • d. All the above

Q. Rolling resistance of a wheel depends upon(i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

a. Only (i) is correct

b. (i) and (ii) are correct

c. (i) and (iii) are correct

d. (ii) and (iii) are correct

  • c. (i) and (iii) are correct

Q. A Milestone chart

a. Shows the interdependencies of variousjobs

b. Depicts the delay of jobs, if any

c. Points outgoing ahead of schedule of jobs, if any

d. None of these

  • d. None of these

Q. Earliest finish of an activity is always

a. Greater than earliest event time of the following node

b. Less than earliest event time of the following node

c. Less than or equal to earliest event time of the following node

d. Greater than or equal to earliest event time of the following node

  • c. Less than or equal to earliest event time of the following node

Q. Critical path lies along the activities having total float

a. Positive

b. Negative

c. Zero

d. Same

  • c. Zero

Q. The critical activity has

a. Maximum float

b. Minimum float

c. Zero float

d. None of these

  • c. Zero float

Q. PERT analysis is based on

a. Optimistic time

b. Pessimistic time

c. Most likely time

d. All the above

  • d. All the above

Q. The most popular type of organisation used for Civil Engineering Constructions, is

a. Line organisation

b. Line and staff organisation

c. Functional organisation

d. Effective organisation

  • a. Line organisation

Q. The probability of completion of any activity within its expected time is

a. 50 %

b. 84.1 %

c. 99.9 %

d. 100 %

  • a. 50 %

Q. The performance of a specific task in CPM, is known

a. Dummy

b. Event

c. Activity

d. Contract

  • c. Activity

Q. Pre-tender stage requires

a. Acquisition of land

b. Selection of site

c. Fmalisation of alignment of work

d. All the above

  • d. All the above

Q. An event is indicated on the network by a number enclosed in

a. A circle

b. A square

c. A triangle

d. All the above

  • d. All the above