Q. A dummy activity

a. Is artificially introduced

b. Is represented by a dotted line

c. Does not consume time

d. All the above

  • d. All the above

Q. The reduction in project time normally results in

a. Decreasing the direct cost and increasing indirect cost

b. Increasing the direct cost and decreasing the indirect cost

c. Increasing the direct cost and indirect cost both

d. Decreasing the direct cost and indirect cost both

  • b. Increasing the direct cost and decreasing the indirect cost

Q. Frederick W. Taylor introduced a system of working known as

a. Line organisation

b. Line and staff organisation

c. Functional organisation

d. Effective organisation

  • c. Functional organisation

Q. The area under the Beta distribution curve is divided into two equal parts by

a. Most likely time

b. Optimistic time

c. Pessimistic time

d. Expected time

  • d. Expected time

Q. CPM is

a. Synthesising in concepts

b. Is built of activities oriented programme

c. Is based on time estimate

d. All the above

  • d. All the above

Q. The Overall in-charge of an organisation at the site responsible for the execution of the works, is

a. Executive Engineer

b. Engineer

c. Junior Engineer

d. Assistant Engineer

  • b. Engineer

Q. The first stage of a construction, is

a. Preparation of estimate

b. Survey of the site

c. Initiation of proposal

d. Preparation of tender

  • c. Initiation of proposal

Q. Crash project duration is obtained by summing the

a. Normal durations for all the activities

b. Crash durations for all activities

c. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

d. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

  • d. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Q. Pick up the correct statement from the following:

a. Forward pass is used for calculating earliest expected time

b. Backward pass is used for calculating the latest occurrence time

c. Maximum value of earliest expected time is used if there is more than one value ofany event

d. All the above

  • d. All the above

Q. Sinking fund is

a. The fund for rebuilding a structure when its economic life is over

b. Raised to meet maintenance costs

c. The total sum to be paid to the municipal authorities by the tenants

d. A part of the money kept in reserve for providing additional structures andstructural modifications

  • a. The fund for rebuilding a structure when its economic life is over

Q. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

a. (a + m + b)/6

b. (a + 2m + b)/6

c. (a + 4m + b)/6

d. (a + 5m + b)/6

  • c. (a + 4m + b)/6