Q. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (Solved)
1. (a + m + b)/6
2. (a + 2m + b)/6
3. (a + 4m + b)/6
4. (a + 5m + b)/6
- c. (a + 4m + b)/6