Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be (Solved)
1. Started 5 days later
2. Completed 5 dayslater
3. Performed at slower rate in 15days
4. All the above
- d. All the above
1. Started 5 days later
2. Completed 5 dayslater
3. Performed at slower rate in 15days
4. All the above