Q. Earliest finish of an activity is always (Solved)

1. Greater than earliest event time of the following node

2. Less than earliest event time of the following node

3. Less than or equal to earliest event time of the following node

4. Greater than or equal to earliest event time of the following node

  • c. Less than or equal to earliest event time of the following node