Q. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be (Solved)

1. 50 %

2. Less than 50 %

3. More than 50 %

4. 100 %

  • c. More than 50 %