Q. Updating may result in (Solved)
1. Change of critical path
2. Decrease of project completion time
3. Increase of project completion time
4. All of the above
- d. All of the above
1. Change of critical path
2. Decrease of project completion time
3. Increase of project completion time
4. All of the above