Q. In resources levelling (Solved)
1. Total duration of project isreduced
2. Total duration of project isincreased
3. Uniform demand of resources is achieved
4. Cost of project is controlled
- c. Uniform demand of resources is achieved
1. Total duration of project isreduced
2. Total duration of project isincreased
3. Uniform demand of resources is achieved
4. Cost of project is controlled