Q. In the time-cost optimisation, using CPM method for network analysis, the crashing of theactivities along the critical path is done starting with the activity having (Solved)
1. Longest duration
2. Highest cost slope
3. Least cost slope
4. Shortest duration
- c. Least cost slope