Q. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,17 and 8 days respectively, The expected time is (Solved)
1. 8 days
2. 9 days
3. 10 days
4. 15 days
- b. 9 days
1. 8 days
2. 9 days
3. 10 days
4. 15 days