Q. A critical ratio scheduling (Solved)
1. Determines the status of each activity
2. Adjusts automatically changes in activity progress
3. Is a dynamic system
4. None of these
- d. None of these
1. Determines the status of each activity
2. Adjusts automatically changes in activity progress
3. Is a dynamic system
4. None of these