Q. Pick up the item whose weight is added to the weight of respective item, is
a. cleats
b. brackets
c. bolts
d. all the above
Q. The expected out turn for earth work in excavation in ordinary soil per workman per day is
a. 1.00 cum
b. 2.00 cum
c. 3.00 cum
d. 4.00 cum
Q. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day,is
a. 1.00 m3
b. 1.25 m3
c. 1.50 m3
d. 1.75 m3
Q. The brick work is measured in sq metre, in case of
a. honey comb brick work
b. brick flat soling
c. half brick walls or the partition
d. all the above
Q. The height of the sink of wash basin above floor level is kept
a. 60 cm
b. 70 cm
c. 75 cm to 80 cm
d. 80 cm
Q. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cementrequired, is
a. 0.200 m3
b. 0.247 m3
c. 0.274 m3
d. 0.295 m3
Q. The item of steel work which is measured in sq.m, is
a. collapsible gates
b. rolling shutters
c. ventilators and glazing
d. all the above
Q. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
a. 0.90 m3
b. 0.94 m3
c. 0.98 m3
d. 1.00 m3
Q. Size, capacity and materials need be specified for
a. bib-cocks
b. stop-cocks
c. ball valves
d. all the above
Q. The expected out turn of half brick partition wall per mason per day is
a. 1.5 m3
b. 2.0 m3
c. 4.0 m2
d. 5.0 m2