Q. The trap which is provided to disconnect the house drain from the street sewer is called

a. master trap

b. intercepting trap

c. interception manhole

d. all the above

  • d. all the above

Q. The expected out turn of 2.5 cm cement concrete floor per mansion per day

a. 2.5 sqm

b. 5.0 sqm

c. 7.5 sqm

d. 10 sqm

  • c. 7.5 sqm

Q. While preparing a detailed estimate

a. dimension should be measured correct to 0.01 m

b. area should be measured correct to 0.01 sqm

c. volume should be measured correct to 0.01 cum

d. all the above

  • d. all the above

Q. The item of the brick structure measured in sq.m, is

a. reinforced brick work

b. broken glass coping

c. brick edging

d. brick work in arches

  • b. broken glass coping

Q. The most reliable estimate is

a. detailed estimate

b. preliminary estimate

c. plinth area estimate

d. cube rate estimate

  • a. detailed estimate

Q. According to ISI method of measurement, the order of the sequence is

a. length, breadth, height

b. breadth, length, height

c. height, length, breadth

d. none of these

  • a. length, breadth, height

Q. Anti-siphonage pipe is connected to

a. main soil pipe

b. bottom of p trap w.c.

c. top of p trap w.

d. side of water closet

  • c. top of p trap w.c.

Q. Pick up the correct statement from the following:

a. bricks are paid per thousand

b. cement is paid per 50 kg bag

c. lime is paid per quintal

d. all the above

  • d. all the above

Q. Pick up the correct statement in case of water supply.

a. pipes laid in trenches and pipes fixed to walls are measured separately

b. cutting through walls and floors are included with the item

c. pipes are classified according to their sizes and quality

d. all the above

  • d. all the above

Q. The concrete work for the following part of the building of specified thickness is measured insquare metres

a. root slabs

b. floors

c. wall panels

d. all the above

  • d. all the above

Q. The expected out turn of 12 mm plastering with cement mortar is

a. 2.5 sq m

b. 4.0 sq m

c. 6.0 sq m

d. 8.0 sq m

  • d. 8.0 sq m

Q. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effectivelength L, is

a. l + 0.42 d

b. l + (2 × 0.42 d)

c. l - (0.42 d)

d. l - (2 × 0.4 d)

  • b. l + (2 × 0.42 d)

Q. The measurement is made for stone work in square metre in case of

a. wall facing

b. columns, lintels, copings

c. building work

d. (a) and (d) of the above

  • d. (a) and (d) of the above