Q. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is (Solved)
1. 0.90 m3
2. 0.94 m3
3. 0.98 m3
4. 1.00 m3
b. 0.94 m3