Q. SSADM means ___________.
a. straight systems analysis design method.
b. structured systems analysis design method.
c. software systems analysis design method.
d. solutions systems analysis design metho
Q. Which are the two levels of development suggested by Booch ?
a. micro and macro processes.
b. inter and intra processes.
c. internal and external processes.
d. small and large processes.
Q. 'Work expands to fill the time available" is _________ law.
a. brooks.
b. peters.
c. parkinson\s.
d. weinbergs
Q. The statement "Putting more people on a late job makes it later" is from_________ law.
a. brooks.
b. peters.
c. parkinson\s.
d. brokers.
Q. KLOC indicates ___________.
a. hundred lines of code.
b. source lines of code.
c. thousand lines of code.
d. million lines of code.
Q. Effort = __________.
a. system size x productivity rate.
b. system size x kloc.
c. person in months / slo
d. person in months x productivity rate.
Q. UFP indicates ________.
a. unused function points.
b. unstructured function points.
c. uniform function points.
d. unadjusted function points.
Q. PERT is _________.
a. process evaluation and review technique.
b. product evaluation and review technique.
c. program evaluation and review technique.
d. project evaluation and review technique.
Q. The activities have zero duration but are assumed to start at the same timeas the first and the end at the same time as the last one is called__________activity.
a. hijacked.
b. heuristic.
c. hammocked.
d. hole.
Q. _________ activities on the network diagram have zero duration and use noresources.
a. dangling.
b. dummy.
c. null.
d. zero.
Q. Every risk is associated with a likely problem and an _______.
a. activity.
b. outcome.
c. action plan.
d. threats.
Q. Risk Management consists of ____________.
a. risk analysis and risk estimation.
b. risk control and risk planning.
c. risk identification and monitoring.
d. risk control, planning, identification and monitoring.
Q. Ranking of the risks and determining risk aversion strategies is called_______.
a. risk analysis.
b. risk control.
c. risk identification.
d. risk evaluation.
Q. ________ = risk likelihood X risk impact.
a. risk estimate.
b. risk expenditure.
c. risk identification
d. risk exposure.
Q. Ranking of the risks and determining risk aversion strategies is called________.
a. risk analysis.
b. risk control.
c. risk identification
d. risk evaluation.