Q. ......................... is activity oriented network diagram.

a. CPM

b. PERT

c. Histogram

d. Ogive

  • a. CPM

Q. ................... is an event oriented network diagram.

a. CPM

b. PERT

c. Histogram

d. Ogive

  • b. PERT

Q. An activity which does not consume either resource or time is called .............................

a. Predecessor activity

b. Successor activity

c. Dummy activity

d. Terminal activity

  • c. Dummy activity

Q. ......................... is a series of activities related to a project.

a. Network

b. Transportation Model

c. Assignment model

d. None of these

  • a. Network

Q. An event which represents the beginning of more than one activity is a :

a. Merge event

b. Net event

c. Burst event

d. None of these

  • c. Burst event

Q. Activities lying on critical path are called ............................

a. Critical activities

b. Non-critical activities

c. Dummy activities

d. None of these

  • a. Critical activities

Q. Activities that cannot be started until one or more of the other activities are completed, arecalled..........................................

a. Dummy activities

b. Initial activities

c. Successor activities

d. Predecessor activities

  • c. Successor activities

Q. ............................ is the sequence of activities which determines the total project duration.

a. Critical path

b. Network

c. Non-critical activities

d. None of these

  • a. Critical path

Q. PERT emphasises on ...........................

a. Activity

b. Time

c. Cost

d. None of these

  • b. Time

Q. ..................... is the duration by which an activity can be delayed without delaying the completionof the project.

a. Earliest Start Time

b. Earliest Finish Time

c. Latest Start Time

d. Latest Finish Time

  • c. Latest Start Time

Q. The EST + activity duration = ..............................

a. Earliest Finish Time

b. Latest Start Time

c. Latest Finish Time

d. None of these

  • a. Earliest Finish Time

Q. ......................... is a scheme or design of something intended to do.

a. Network

b. Float

c. Project

d. Program

  • a. Network

Q. In a network diagram, activity is denoted by ............................

a. Node

b. Arrow

c. Triangle

d. None of these

  • b. Arrow

Q. .......................... is the duration by which an activity can be delayed without delaying the project.

a. Slack

b. Total float

c. Both a and b

d. None of these

  • b. Total float