Q. ..................... is the duration by which an activity can be delayed without delaying the completionof the project. (Solved)

1. Earliest Start Time

2. Earliest Finish Time

3. Latest Start Time

4. Latest Finish Time

  • c. Latest Start Time
Subscribe Now

Get All Updates & News