Q. ……………is the duration by which an activity can be delayed without delaying theproject

a. slack

b. total float

c. free float

d. independent float

  • b. total float

Q. ……….is activity oriented.

a. cpm

b. pert

c. lp

d. none of the above

  • a. cpm

Q. ………. is event oriented.

a. cpm

b. pert

c. lp

d. none of the above

  • b. pert

Q. PERT emphasis on ………..

a. time

b. activity

c. a) and b)

d. none of the above

  • a. time

Q. Full form of PERT is

a. performance evaluation review technique

b. programme evaluation review technique

c. programme evaluation research technique

d. none of these.

  • b. programme evaluation review technique

Q. …….. is a scheme or design of something intended or device.

a. programme

b. project

c. network

d. float

  • c. network

Q. An activity which must be completed before one or more other activities start is knownas …………activity.

a. dummy

b. predecessor

c. successor

d. none of these

  • b. predecessor

Q. The event is commonly represented by …… in network diagram

a. nodes

b. arrow

c. triangle

d. none of these

  • a. nodes

Q. …………..is an activity oriented diagram.

a. cpm

b. pert

c. histogram

d. none of the above

  • a. cpm

Q. ………… is the duration by which an activity can be delayed without delaying theproject.

a. total float

b. slack

c. earliest event time

d. none of these

  • a. total float

Q. ………is the shortest possible time in which an activity can be delayed withoutdelaying the project.

a. pessimistic time estimate

b. optimistic time estimate

c. most likely time estimate

d. none of these

  • b. optimistic time estimate

Q. Which of the following is not a part of decision tree problem specification?

a. a list of alternatives

b. a list of possible state of nature

c. evpi

d. pay off associated with alternative/ state of nature combination.

  • c. evpi