Top 150+ Solved Construction Project Management MCQ Questions Answer

From 106 to 120 of 149

Q. Contract is terminated in case of

a. Slow progress and time limit exceeds

b. Work is not being executed as per specifications and instruction of EIC

c. Contractor tries to admit sub-contractor

d. All of the above

  • d. All of the above

Q. Mobilization advance

a. Shall be 2 to 5 % of project cost.

b. Shall be 3 to 7 % of project cost.

c. Shall be 10 to 15 % of project cost.

d. Shall be 12 to 18 % of project cost.

  • a. Shall be 2 to 5 % of project cost.

Q. PERT analysis is based upon

a. Optimistic time

b. Pessimistic time

c. Most likely time

d. All of the above

  • d. All of the above

Q. The time activity consumes in most adverse conditions is

a. Optimistic time

b. Pessimistic time

c. Most likely time

d. All of the above

  • b. Pessimistic time

Q. The time activity consumes in normal conditions is

a. Optimistic time

b. Pessimistic time

c. Most likely time

d. All of the above

  • c. Most likely time

Q. The difference between the total float and free float is called

a. Duration

b. Interfering float

c. Critical activity

d. None of the above

  • b. Interfering float

Q. The critical path is

a. The longest path of the network

b. The shortest path of the network

c. The average duration path of the network

d. None of the above

  • a. The longest path of the network

Q. The float of critical activity is always

a. Maximum

b. Minimum

c. Zero

d. None of the above

  • c. Zero

Q. A dummy activity in a network

a. Is represented by dotted line

b. Is an artificial activity

c. Does not consume time and resources

d. All of the above

  • d. All of the above

Q. Activity starts from

a. Head event

b. Tail event

c. Dual role event

d. None of the above

  • b. Tail event

Q. Which of the following is an activity

a. Excavation

b. Curing

c. Laying concrete

d. All of the above

  • d. All of the above

Q. Earliest start time of activity equals to

a. TE of tail event of an activity

b. TE of head event of an activity

c. Average time of TE of tail event and head event

d. None of the above

  • a. TE of tail event of an activity
Subscribe Now

Get All Updates & News