Q. In which type of tender advantage of keen bidding competition can be availed.

a. Open tender or public tender

b. Selected tender

c. Negotiated tender

d. None of the above

  • a. Open tender or public tender

Q. What SMB stands for?

a. Short measurement book

b. Salient measurement book

c. Standard measurement book

d. None of the above

  • c. Standard measurement book

Q. SD, mobilization advance and cost of materials given to contractor will be deducted from

a. RA bill

b. Final bill

c. EMD

d. None of the above

  • a. RA bill

Q. What EMD stands for?

a. Exact money deposit

b. Earnest money deposit

c. Exact money deduction

d. Exact monthly deduction

  • b. Earnest money deposit

Q. Which of the following contract is most suitable for road and bridges?

a. BOT contract

b. Cost plus fixed fee contract

c. All in one contract

d. Labour contract

  • a. BOT contract

Q. In which of the following contract; contractor tries to complete job quickly?

a. Item rate contract

b. Cost plus fixed fee contract

c. All in one contract

d. Labour contract

  • b. Cost plus fixed fee contract

Q. In which of the following contract; contractor is quickly be agreed and work on job?

a. Cost plus percentage rate contract

b. Lump sum contract

c. Piece work agreement

d. Labour contract

  • a. Cost plus percentage rate contract

Q. In which of the following contract; contractor is not required to deposit SD?

a. Item rate contract

b. Lump sum contract

c. Piece work agreement

d. Labour contract

  • c. Piece work agreement

Q. In which of the following contract; contractor is required to offer a fixed sum for job in allrespect as per given drawings and details?

a. Item rate contract

b. Lump-sum contract

c. All in one contract

d. Labor contract

  • b. Lump-sum contract

Q. Extra items will cause headache in item rate contract

a. Right

b. Wrong

c. none

d. all

  • a. Right

Q. Which of the following is/are advantages of item rate contract

a. Elasticity and fair to both the parties

b. Economical

c. Absence of uncertainties

d. All of the above

  • d. All of the above

Q. Specialized work needs departmental execution

a. Right

b. Wrong

c. none

d. all

  • b. Wrong

Q. Contract system is suitable for big projects

a. Right

b. Wrong

c. none

d. all

  • a. Right

Q. Departmental execution is suitable for small jobs

a. Right

b. Wrong

c. none

d. all

  • a. Right

Q. Which of the following is not essential requirement for contract

a. Parties must be competent

b. Should be made by free consent

c. There shall be definite and legal proposal and its acceptance.

d. Both Parties must be citizens of same country

  • d. Both Parties must be citizens of same country