Top 150+ Solved Operations Management and Strategic Management MCQ Questions Answer

From 46 to 60 of 124

Q. To decide work load for men and machines:

a. Medium range forecasting is used

b. Short term forecasting is used

c. Long range forecasting is used

d. A combination of long range and medium range forecasting is use

  • b. Short term forecasting is used

Q. Important factor in forecasting production is:

a. Environmental changes

b. Available capacity of machines

c. Disposable income of the consumer

d. Changes in the preference of the consumer.

  • b. Available capacity of machines

Q. Application of technology or process to the raw material to add use value is knownas:

a. Product

b. Production

c. Application of technology

d. Combination of technology and process.

  • b. Production

Q. In Production by disintegration the material undergoes:

a. Change in economic value only

b. Change in physical and chemical characteristics

c. Change in technology only

d. None of the above.

  • b. Change in physical and chemical characteristics

Q. In Production by service, the product undergoes the changes in:

a. Shape and size of the surface

b. Shape of the surface only

c. Size of the surface only

d. Chemical and Mechanical properties.

  • d. Chemical and Mechanical properties.

Q. Use of any process or procedure designed to transform a set of input elements into aset of output elements is known as:

a. Transformation process

b. Transformation of input to output

c. Production

d. Technology change

  • c. Production

Q. Conversion of inputs into outputs is known as:

a. Application of technology

b. Operations management

c. Manufacturing products

d. Product

  • b. Operations management

Q. The desired objective of Production and Operations Management is:

a. Use cheap machinery to produce

b. To train unskilled workers to manufacture goods perfectly

c. Optimal utilisation of available resources

d. To earn good profits.

  • c. Optimal utilisation of available resources

Q. The scope of Production Planning and Control is:

a. Limited to Production of products only

b. Limited to production of services only

c. Limited to production of services and products only

d. Unlimited, can be applied to any type of activity.

  • d. Unlimited, can be applied to any type of activity.

Q. Manufacturing system often produces:

a. Standardised products

b. Standardised products in large volumes

c. Substandardproducts in large volumes

d. Products and services in limited volume.

  • a. Standardised products

Q. The difference between product system and project system is:

a. Project system the equipment and machinery are fixed where as in product system they are movable

b. In Product system the machinery and equipment are fixed and in project system they are not fixed

c. Project system produces only standardized products and product system produces only unstandardised products

d. Products cannot be stocked whereas projects can be stocke

  • b. In Product system the machinery and equipment are fixed and in project system they are not fixed

Q. Most important benefit to the consumer from efficient production system is:

a. He can save money

b. He will have product of his choice easily available

c. He gets increased use value in the product

d. He can get the product on credit.

  • c. He gets increased use value in the product

Q. Two important functions that are to be done by Production department are:

a. Forecasting

b. Costing

c. Scheduling and loading

d. Inspecting.

  • c. Scheduling and loading

Q. The act of releasing the production documents to the production department isknown as:

a. Planning

b. Routing

c. Dispatching

d. Releasing

  • c. Dispatching

Q. The activity of specifying when to start the job and when to end the job is known as:

a. Planning

b. Scheduling

c. Timing

d. Follow-up.

  • b. Scheduling