Q. A critical path network diagram does NOT: (Solved)
1. Help determine the amount of float
2. Identify the particularly important activities
3. Calculate earned value
4. Calculate the duration of the whole project
- c. Calculate earned value
1. Help determine the amount of float
2. Identify the particularly important activities
3. Calculate earned value
4. Calculate the duration of the whole project