Q. Which one of the following best describes a project issue? (Solved)
1. A major problem that requires formal escalation.
2. A problem that the project manager has to deal with on a day-to-day basis.
3. An uncertain event that may or may not occur.
4. An opportunity that occurs through change control.
- a. A major problem that requires formal escalation.