Q. Which of the following is not a tool and technique used in the process of Plan Risk Responses (Solved)
1. Contingent Response Strategies
2. Expert Judgment
3. Risk and Impact Matrix
4. Strategies for positive risks or opportunities
- c. Risk and Impact Matrix