Q. Which among the following methods is used when both distance and load have to be considered for optimality in terms of cost? (Solved)
1. Factor rating
2. Rating plan
3. Centre of gravity
4. Point rating
- c. Centre of gravity
1. Factor rating
2. Rating plan
3. Centre of gravity
4. Point rating