Q. Use of sequencing role shortest processing time generally result in (Solved)
1. Minimum average lateness
2. Maximum utilization
3. Maximum effectiveness
4. Minimum average flow time
- d. Minimum average flow time
1. Minimum average lateness
2. Maximum utilization
3. Maximum effectiveness
4. Minimum average flow time