Q. Which scheduling technique should be employed when due dates are important for a job order ? (Solved)
1. Forward scheduling
2. Loading
3. Dispatching
4. Backward scheduling
- d. Backward scheduling
1. Forward scheduling
2. Loading
3. Dispatching
4. Backward scheduling