Q. During the month of December actual direct labour cost amounted to $39,550, the standard direct labour rate was $10 per hour and the direct labour rate variance amounted to $450 favourable. The actual direct labour hours worked were: (Solved)

1. 3,955 hours

2. 4,000 hours

3. 3,910 hours

4. 4,500 hours

  • b. 4,000 hours