Q. Match the columns(i) Activity Ratio -------------------- i) (Actual hours worked / Budgeted hours) * 100(ii) Capacity Ratio ------------------ ii) (Standard hours of actual production / Actual hours worked) * 100(iii) Efficiency Ratio ----------------- iii) (Standard hours for actual output / Budgeted hours) * 100 (Solved)
1. A-ii, B-iii, C-i
2. A-i, B-ii, C-iii
3. A-iii, B-i, C-ii
4. None of the above
- c. A-iii, B-i, C-ii