Q. For a project, benefit cost ratio is equal to one, then (Solved)
1. IRR will be greater than one
2. IRR will be greater than discount rate
3. IRR will be less than discount rate
4. IRR will be equal to discount rate
- d. IRR will be equal to discount rate