Q. Estimated time required in normal conditions complete an activity is -----------------. (Solved)
1. Pessimistic time
2. Optimistic time
3. Most likely time
4. None of these.
- c. Most likely time
1. Pessimistic time
2. Optimistic time
3. Most likely time
4. None of these.