Q. _____________ is used to accomplish the project economically in the minimum availabletime with limited resources (Solved)
1. Project Scheduling.
2. Network Analysis.
3. Budget Analysis.
4. Critical Planning
- a. Project Scheduling.
1. Project Scheduling.
2. Network Analysis.
3. Budget Analysis.
4. Critical Planning