Q. The activities have zero duration but are assumed to start at the sametime as the first and the end at the same time as the last one iscalled__________ activity. (Solved)
1. hijacked.
2. heuristic.
3. hammocked.
4. hole.
- c. hammocked.
1. hijacked.
2. heuristic.
3. hammocked.
4. hole.