Q. The shortest time in which we could expect to complete the activity, barringoutright miracles are called ________. (Solved)
1. optimistic time.
2. pessimistic time.
3. most likely time.
4. shortest time.
- a. optimistic time.
1. optimistic time.
2. pessimistic time.
3. most likely time.
4. shortest time.