Q. When prior to the due date of performance, the promisor absolutely refuses to performthe contract, it is known as: (Solved)
1. Abandonment of a contract
2. Remission of contract
3. Actual breach of contract
4. Anticipatory breach of contract
- d. Anticipatory breach of contract