Q. The assumption in PERT is (Solved)
1. A project is always behind schedule
2. Cost of project is always more than the estimated cost
3. A project can be sub-divided into a set of predictable, independent activities
4. Activities are complex in nature and time taken by them are indeterminate
5. None of the above
- c. A project can be sub-divided into a set of predictable, independent activities