Q. The assumption in PERT is (Solved)

1. A project is always behind schedule

2. Cost of project is always more than the estimated cost

3. A project can be sub-divided into a set of predictable, independent activities

4. Activities are complex in nature and time taken by them are indeterminate

5. None of the above

  • c. A project can be sub-divided into a set of predictable, independent activities