Top 350+ Solved Software Project Management (SPM) MCQ Questions Answer

From 61 to 75 of 371

Q. Which type of software engineering team has a defined leader who coordinates specific tasks and secondary leaders that have responsibility for sub tasks?

a. controlled decentralized (cd)

b. democratic decentralized (dd)

c. controlled centralized (cc)

d. none of the mentioned

  • a. controlled decentralized (cd)

Q. Commitments to unrealistic time and resource estimates may result in

a. project delay

b. poor quality work

c. project failure

d. all of the mentioned

  • d. all of the mentioned

Q. Which software engineering team has no permanent leader?

a. controlled decentralized (cd)

b. democratic decentralized (dd)

c. controlled centralized (cc)

d. none of the mentioned

  • b. democratic decentralized (dd)

Q. Which of the following is not a project factor that should be considered when planning the structure of software engineering teams?

a. the difficulty of the problem to be solved

b. high frustration caused by personal, business, or technological factors that causes friction among team members

c. the degree of sociability required for the project

d. the rigidity of the delivery date

  • c. the degree of sociability required for the project

Q. Which of the following is a collection of project coordination technique?

a. formal approaches

b. formal, interpersonal procedures

c. informal, interpersonal procedures

d. all of the mentioned

  • d. all of the mentioned

Q. Which activity sits at the core of software requirements analysis?

a. problem decomposition

b. partitioning

c. problem elaboration

d. all of the mentioned

  • d. all of the mentioned

Q. Which of the following is not a sign that indicates that an information systems project is in jeopardy?

a. software people don’t understand their customers needs

b. changes are managed poorly

c. sponsorship is gained

d. users are resistant

  • c. sponsorship is gained

Q. SPMP stands for

a. software project manager’s plan

b. software project management plan

c. software product management plan

d. software product manager’s plan

  • b. software project management plan

Q. Which of the following categories is part of the output of software process?

a. computer programs

b. documents that describe the computer programs

c. data

d. all of the mentioned

  • d. all of the mentioned

Q. 4 COST MONITORING

a. baselines

b. source code

c. data model

d. none of the mentioned

  • a. baselines

Q. Software Configuration Management can be administered in several ways. These include

a. a single software configuration management team for the whole organization

b. a separate configuration management team for each project

c. software configuration management distributed among the project members

d. all of the mentioned

  • a. a single software configuration management team for the whole organization

Q. What combines procedures and tools to manage different versions of configuration objects that are created during the software process?

a. change control

b. version control

c. scis

d. none of the mentioned

  • b. version control

Q. What complements the formal technical review by assessing a configuration object for characteristics that are generally not considered during review?

a. software configuration audit

b. software configuration management

c. baseline

d. none of the mentioned

  • a. software configuration audit

Q. Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system?

a. system building

b. release management

c. change management

d. version management

  • a. system building

Q. Which of the following option is not tracked by configuration management tools?

a. tracking of change proposals

b. storing versions of system components

c. tracking the releases of system versions to customers

d. none of the mentioned

  • d. none of the mentioned