Top 550+ Solved Principles of Management MCQ Questions Answer
Q. ……….is the latest time by which an activity can be finished without delaying thecompletion of the project.
a. EST
b. EFT
c. LST
d. LFT
Q. ……………is the duration by which an activity can be delayed without delaying the project
a. Slack
b. Total float
c. Free float
d. Independent float
Q. ……… is the time by which the completion of an activity can be delayed beyond itsearliest finish time without affecting the earliest start time of a succeeding activity
a. Slack
b. Total float
c. Free float
d. Independent float
Q. Full form of PERT is
a. Performance evaluation review technique
b. Programme Evaluation Review technique
c. Programme Evaluation Research Technique
d. None of these.
Q. …….. is a scheme or design of something intended or device.
a. Programme
b. Project
c. Network
d. Float
Q. An activity which must be completed before one or more other activities start is known as …………activity.
a. Dummy
b. Predecessor
c. Successor
d. None of these
Q. The event is commonly represented by …… in network diagram
a. Nodes
b. Arrow
c. Triangle
d. None of these
Q. …….is the disconnection of an activity before the completion of activities in a projectnetwork diagram.
a. Dangling
b. Looping
c. Dummy
d. None of the above
Q. ………… is the duration by which an activity can be delayed without delaying theproject.
a. Total float
b. Slack
c. Earliest event time
d. None of these
Q. ………is the shortest possible time in which an activity can be delayed withoutdelaying the project.
a. Pessimistic time estimate
b. Optimistic time estimate
c. Most likely time estimate
d. None of these
Q. Which of the following is not a part of decision tree problem specification?
a. a list of alternatives
b. A list of possible state of nature
c. EVPI
d. Pay off associated with alternative/ state of nature combination.