Q. The uplift pressure on the face of a drainage gallery in a dam is taken as

a. hydrostatic pressure at toe

b. average of hydrostatic pressure at toe and heel

c. two-third of hydrostatic pressure at toe plus one-third of hydrostatic pressure at heel

d. none of the above

  • c. two-third of hydrostatic pressure at toe plus one-third of hydrostatic pressure at heel

Q. Horizontal acceleration due to earthquake results in

a. hydrodynamic pressure

b. inertia force into the body of the dam

c. both (a) and (b)

d. none of the above

  • c. both (a) and (b)

Q. Hydrodynamic pressure due to earthquake acts at a height of

a. 3H/47I above the base

b. 3H747t below the water surface

c. 4H/371 above the base

d. 4H737t below the water surface where H is the depth of water.

  • c. 4H/371 above the base

Q. The major resisting force in a gravity dam is

a. water pressure

b. wave pressure

c. self-weight of dam

d. uplift pressure

  • c. self-weight of dam

Q. When the reservoir is full, the maximum compressive force in a gravity dam is produced

a. at the toe

b. at the heel

c. within the middle third of base

d. at centre of base

  • a. at the toe

Q. As compared to gravity dams, earthen dams

a. are costlier

b. are less susceptible to failure

c. require sound rock foundations

d. require less skilled labour

  • d. require less skilled labour

Q. The most suitable material for the central impervious core of a zoned embankment typedam is

a. clay

b. coarse sand

c. silty clay

d. clay mixed with fine sand

  • d. clay mixed with fine sand

Q. Seepage through embankments in an earthen dam is controlled by

a. drainage filters

b. relief wells

c. drain trenches

d. provision of downstream berms

  • c. drain trenches

Q. Seepage through foundation in an earthen dam is controlled by providing

a. rock toe

b. horizontal blanket

c. impervious cut off

d. chimney drain

  • c. impervious cut off

Q. The flow of water after spilling over the weir crest in chute spillway and side channelspillway respectively are

a. at right angle and parallel to weir crest

b. parallel and at right angle to weir crest

c. parallel to weir crest in both

d. at right angle to weir crest in both

  • a. at right angle and parallel to weir crest