Q. Identify the circumstances where under- or over-recovery of overhead will occur:

a. Actual overhead costs are different from budgeted overheads

b. The actual activity level is different from the budgeted activity level

c. Actual overhead costs and actual activity level differ from the budgeted costs and level

d. All of the above

  • c. Actual overhead costs and actual activity level differ from the budgeted costs and level

Q. The loss incurred on an incomplete contract is transferred to …………….account.

a. Costing profit and loss account

b. profit and loss account

c. trading account

d. deferred to next year.

  • a. Costing profit and loss account

Q. When the completion stage of the contract is more than half, the profit to be creditedto Profit and Loss account will be equal to…………..

a. 1/3rd of Notional Profit x cash received Work certified

b. ½ of Notional Profit x cash received Work certified

c. 2/3rd of Notional profit x cash received Work certified

d. full Notional Profit.

  • c. 2/3rd of Notional profit x cash received Work certified

Q. Contract costing is not used in one of the following industries.

a. Ship building

b. Civil Construction

c. Automobiles

d. Construction of Bridges

  • c. Automobiles

Q. The sum of value of work certified and uncertified appearing in the Contract Accountis called ……………..

a. Work done.

b. Work in Process

c. Work Completed

d. Work in Progress

  • d. Work in Progress

Q. Total costs incur in a production process, is divided by total number of output units tocalculate the

a. unit costs

b. cost of direct material

c. cost of direct labour

d. cost of indirect labour

  • a. unit costs

Q. WIP in contract means:

a. Work certified

b. Work certified and work uncertified

c. Cash received

d. None of these

  • b. Work certified and work uncertified

Q. Profit remaining as reserve is :

a. Transfer to p/L

b. Deducted from WIP

c. Not taken into account.

d. Deducted from cost of the contract.

  • c. Not taken into account.

Q. Profit in incomplete contract in known as notional profit because:

a. It is not real profits

b. Real profit is ascertain when the contract is complete

c. There is no such incomplete contract.

d. The profit is only an approximation.

  • d. The profit is only an approximation.

Q. The contract undertaken are completed away from the ………………premises.

a. Contractors

b. Contractee

c. Party

d. Builder

  • a. Contractors

Q. A contract is generally of ………………..duration.

a. Long

b. Small

c. Average

d. Very Small

  • a. Long