Q. SMI = [Mt – (Fa + Fc + Fd)]/Mt. Here Mt is the number of modules

a. in the current release

b. in the current release that have been changed

c. from the preceding release that were deleted in the current release

d. none of the mentioned

  • a. in the current release

Q. The amount of time that the software is available for use is known as

a. reliability

b. usability

c. efficiency

d. functionality

  • a. reliability

Q. Usability in metric analysis is defined as the degree to which the software

a. stated needs

b. is easy to use

c. makes optimal use of system resources

d. none of the mentioned

  • b. is easy to use

Q. Which of the following is incorrect activity for the configuration management of a software system?

a. internship management

b. change management

c. version management

d. system management

  • a. internship management

Q. Which of the following is the reason that software is delivered late?

a. changing customer requirements that are not reflected in schedule changes

b. technical difficulties that could not have been foreseen in advance

c. human difficulties that could not have been foreseen in advance

d. all of the mentioned

  • d. all of the mentioned

Q. Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks?

a. software macroscopic schedule

b. software project scheduling

c. software detailed schedule

d. none of the mentioned

  • b. software project scheduling

Q. Every task that is scheduled should be assigned to a specific team member is termed as

a. compartmentalization

b. defined milestones

c. defined responsibilities

d. defined outcomes

  • c. defined responsibilities

Q. What is a collection of software engineering work tasks, milestones, and deliverables that must be accomplished to complete a particular project?

a. task set

b. degree of milestone

c. adaptation criteria

d. all of the mentioned

  • a. task set

Q. Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as

a. time allocation

b. effort validation

c. defined milestone

d. effort distribution

  • b. effort validation

Q. What is used to determine the recommended degree of rigor with which the software process should be applied on a project?

a. degree of rigor

b. adaptation criteria

c. task set

d. both degree of rigor and adaptation criteria

  • b. adaptation criteria

Q. What evaluates the risk associated with the technology to be implemented as part of project scope?

a. concept scoping

b. preliminary concept planning

c. technology risk assessment

d. customer reaction to the concept

  • b. preliminary concept planning

Q. Which of the following is not an adaptation criteria for software projects?

a. size of the project

b. customers complaints

c. project staff

d. mission criticality

  • b. customers complaints

Q. Which of the following is a project scheduling method that can be applied to software development?

a. pert

b. cpm

c. cmm

d. both pert and cpm

  • d. both pert and cpm