Top 1000+ Solved Software Engineering MCQ Questions Answer
Q. Which of the following is not an adaptation criteria for software projects?
a. size of the project
b. customers complaints
c. project staff
d. mission criticality
Q. Which of the following is a project scheduling method that can be applied to software development?
a. pert
b. cpm
c. cmm
d. both pert and cpm
Q. A technique for performing quantitative analysis of progress is known as
a. bcws
b. eva
c. bac
d. cbse
Q. What is the recommended distribution of effort for a project?
a. 40-20-40
b. 50-20-30
c. 30-40-30
d. 50-30-20
Q. A project usually has a timeline chart which was developed by
a. henry gantt
b. barry boehm
c. ivar jacabson
d. none of the mentioned
Q. Risk management is one of the most important jobs for a
a. client
b. investor
c. production team
d. project manager
Q. Which of the following risk is the failure of a purchased component to perform as expected?
a. product risk
b. project risk
c. business risk
d. programming risk
Q. Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.”?
a. technology change
b. product competition
c. requirements change
d. none of the mentioned
Q. What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk?
a. risk monitoring
b. risk planning
c. risk analysis
d. risk identification
Q. Which of the following risks are derived from the organizational environment where the software is being developed?
a. people risks
b. technology risks
c. estimation risks
d. organizational risks
Q. Which of the following risks are derived from the software or hardware technologies that are used to develop the system?
a. managerial risks
b. technology risks
c. estimation risks
d. organizational risks
Q. Which of the following term is best defined by the statement: “Derive traceability information to maximize information hiding in the design.”?
a. underestimated development time
b. organizational restructuring
c. requirements changes
d. none of the mentioned
Q. Which of the following strategies means that the impact of the risk will be reduced?
a. avoidance strategies
b. minimization strategies
c. contingency plans
d. all of the mentioned
Q. 6 IDENTIFICATION- RMMM PLAN-CASE TOOLS
a. threats
b. vulnerabilities
c. consequences
d. all of the mentioned