Q. If the standard length of a B.G. crossing is 597 cm, the number of crossing, is

a. 1 in 8½

b. 1 in 12

c. 1 in 16

d. None of these

  • b. 1 in 12

Q. Switch angle is the angle between

a. The gauge face of the stock rail and tongue rail

b. The outer face of the stock rail and tongue rail

c. The gauge face of the stock rail and outer face of the tongue rail

d. The outer face of the stock rail and the gauge face of the tongue rail

  • a. The gauge face of the stock rail and tongue rail

Q. On Broad Gauge main lines with maximum traffic loads, the rail section preferred to, is

a. 29.8 to 37.3 kg/m

b. 32.5 to 42.5 kg/cm

c. 44.7 to 56.8 kg/m

d. None of these

  • c. 44.7 to 56.8 kg/m

Q. The treadle bar is provided

a. In the middle of the track a little in front of the toes of the tongue rail

b. Near and parallel to inner side of one of the rails

c. At right angle to the rail

d. Near and parallel to inner side of both the rails

  • b. Near and parallel to inner side of one of the rails

Q. Heel of crossing is the line joining

a. Ends of splice rail and point rail

b. Ends of lead rails butting the crossing

c. Ends of wing rails

d. Throat and actual nose of crossing

  • a. Ends of splice rail and point rail

Q. The main advantage of a cement concrete sleeper, is:

a. Its heavy weight which improves the track modulus

b. Its capacity to maintain gauge

c. Its suitability for track circuiting

d. All the above

  • d. All the above

Q. Stock rails are

a. Parts of crossing

b. Fitted against check rails

c. Fitted against tongue rails

d. Laid between heel of switch and nose of crossing

  • c. Fitted against tongue rails

Q. Continuity of electric current across welded rail joints, is maintained by

a. Welding ends of a wire to each rail

b. Placing an insulated plate underneath the rails

c. Placing insulation in expansion gaps

d. None of these

  • d. None of these

Q. The arrangement of rails which permit trains to cross another track and also to divert to the other track, is called

a. Diamond crossing

b. Diamond crossing with single slip

c. Diamond crossing with double slip

d. Cross over

  • c. Diamond crossing with double slip

Q. A CST-9 sleeper consists of

a. Two inverted triangular pots on either side of rail seat

b. A central plate with a projected key and box on the top of plate

c. A tie bar and 4 cotters to connect two cast iron plates

d. All the above

  • d. All the above

Q. Staggered rail joints are generally provided

a. On curves

b. On tangents

c. On bridges

d. In tunnels

  • a. On curves