Q. In the project environment, the individual ultimately responsible for quality controlis: (Solved)
1. The line workers who must strive "to do things right the first time" to avoid quality problems
2. The company's quality control manager who must work with the project members to ensure the quality control program is effective
3. The head of the production department who retains ultimate quality control responsibility for all the company's projects
4. The project manager who has ultimately responsibility for the entire project
- d. The project manager who has ultimately responsibility for the entire project