Q. In pretensioning system (Solved)

1. the member is cast fist followed by tensioning of high-tensile wires

2. the member is prestressed by external anchors

3. the high-tensile wires are tensioned before placing concrete in forms

4. none of the above

  • c. the high-tensile wires are tensioned before placing concrete in forms