Q. In pretensioning system (Solved)
1. the member is cast fist followed by tensioning of high-tensile wires
2. the member is prestressed by external anchors
3. the high-tensile wires are tensioned before placing concrete in forms
4. none of the above
- c. the high-tensile wires are tensioned before placing concrete in forms